We have made a lot of progress in just the first week! First, we got the excavator out there to level an area for the workshop and the house. Then we had him bring rock in for a temporary driveway and parking area in case it rains. Next we met with the workshop guy to get that all squared away and pick out our colors and options. He should be able to start building it in two weeks which Shannon is VERY excited about! We also got a port-a-potty delivered. Sorry I don’t have a picture of that but you can use your imagination =P. Lastly, we got in touch with the foundation company and got on their schedule. They already came out today to get started on placing all the forms. So exciting to see it coming together! I think we did a lot for just the first 4 days!
The boys loved watching the bulldozer and dump trucks.
Next week we will have the piers put in for the foundation (we have a ton of those), rough in the plumbing and floor electrical and get a form survey. After that, we will be ready to pour the slab!